35 workers are employed to complete a construction
project in 16 days. before the project starts, the boss
of the company is told that he needs to complete
the project in 14 days. assuming that all the workers
work at the same rate, how many more workers does
he need to employ in order to complete the project
on time?
Answers: 1
ANSWER
By inverse proportion,
28×x=35×16
x=
28
35×16
=20 days
Step-by-step explanation:
Plzz mark me as Brainliest!!
5 workers need to complete the construction. Total 40 Workers need.